Toronto Transit Commission (TTC) crews completed significant and complex state-of-good-repair and modernization work during a temporary suspension of subway service between Oct. 10-11.
Service was suspended on Line 2 Bloor-Danforth between the Kipling and Jane stations and St. George and Broadview stations during the planned replacement of one beam and two structural support bearings on the Prince Edward (Bloor) Viaduct. During the beam replacement, crews discovered that one of the concrete pads supporting the beam had deteriorated and also needed to be replaced.
Crews have replaced four similar beams so far this year, with one more repair scheduled before the end of the year.